ScheduleInsight Generated report
ScheduleInsight · Acceleration Plan

Tower C — Commercial Tower & Podium

Programme R12 — least-cost compression against a £700,000 acceleration budget

−102 days for 692,925
BUDGET EXHAUSTED
Client
Meridian Estates (owner)
Contractor
Calderwood Construction Ltd
Contract
JCT D&B 2016
Programme
R12 — data date 28 Feb 2026
Acceleration budget
£700,000
Activities
233
Current finish
2029-02-20
Accelerated finish
2028-11-10
Report reference
SI-AP-EX-009
ScheduleInsight
Parsed on-device · file never uploaded
Tower C · R12 · Acceleration Plan28 Feb 2026

Contents

Report
01The decision3
02Basis and assumptions4
03The acceleration plan5
04Cost-efficiency curve6
05Method, basis and limitations7
Appendices — supporting detail
AStep-by-step compression log8
How to read this report

Page 1 states what the acceleration costs and what it buys, and is sufficient on its own. Page 2 carries the assumptions every figure rests on and should be read before the plan is quoted. Page 3 is the plan itself, in the order it should be actioned.

Costs are shown in the schedule’s own units; the file does not record a currency.

ScheduleInsight · Acceleration Plan2
1 · The decision28 Feb 2026

01 The decision

This report sets out what it would cost to bring Tower C — Commercial Tower & Podium in, and what that spend actually buys. The plan below was produced by compressing the critical path one verified step at a time: after every change the schedule was re-scheduled in full and the step kept only if the finish date genuinely moved.

Forecast finish
2029-02-20

Before any acceleration, on the schedule as issued.

Accelerated finish
2028-11-10

102 days earlier.

Cost of the plan
692,925

Across 53 interventions, in the schedule’s own cost units.

Cost per day bought
6,793

Averaged over the whole plan; the marginal rate rises as it runs.

Why the plan stopped

BUDGET EXHAUSTED. Budget exhausted. The next compression step costs 12150 and there was 7075 left.

Where the money stops working. Spending is efficient up to roughly 200,850, which buys 47 days. Past that point a day first costs more than twice the 4,930 the opening steps paid, and the same days are being bought at a worse price. If the acceleration has to be part-funded, that is the natural place to draw the line.

ScheduleInsight · Acceleration Plan3
2 · Basis and assumptions28 Feb 2026

02 Basis and assumptions

Read this page before the plan. A P6 or MS Project file records how long work is planned to take and what it is budgeted to cost. It does not record how far that work could be compressed, or what compressing it would cost — those are commercial judgements that live outside the schedule. Two stated assumptions stand in for them, and every figure in this report moves if either is changed.

AssumptionValue usedWhat it means
Maximum compression30%No activity was shortened by more than this share of its duration.
Acceleration premium1.5×A crashed day was costed at this multiple of the activity’s planned daily rate.
Rate basisBudgeted costDaily rates were derived from each activity’s own budgeted cost in the file.
Minimum duration1dNo working activity was compressed below this floor.
Currency

Costs are shown in the units the schedule was built in. Neither XER nor PMXML records a currency, so none is stated here rather than assumed.

What could be compressed

Of 233 activities in the schedule, 232 were eligible for compression. The remainder were held back for the reasons below.

Held back because it is…Activities
summary or level-of-effort rows1

How the compression was chosen

At each step the analysis takes the critical network, splits it into the separate chains that are independently setting the finish date, and compresses the cheapest eligible activity on each of them together. It then re-schedules and keeps the step only if the finish moved; if it did not, the set is widened and retried.

This matters because the textbook method — compress the single cheapest critical activity, repeat — is only correct when the critical path is one chain. Where two chains run in parallel, shortening one leaves the other setting the date and the money buys nothing. This programme has that condition: 40 of the 53 interventions below compress two or more parallel chains at once, and would each have been wasted spend if taken singly.

ScheduleInsight · Acceleration Plan4
3 · The plan28 Feb 2026

03 The acceleration plan

The interventions below are listed in the order the analysis chose them, cheapest days first. Each row is a single instruction: shorten the named activity (or activities) by the stated number of days. The finish column shows where the programme lands once that row is done, so the plan can be stopped part-way at any row and the outcome read directly.

#CompressDaysCostCumulativeFinish
1FIT-1000 Interior fit-out — zone 115,1005,1002029-02-19
2FIT-1000 Interior fit-out — zone 1
FIT-1010 Interior fit-out — zone 2 parallel
36,12011,2202029-02-16
3FIT-1010 Interior fit-out — zone 2
FIT-1020 Interior fit-out — zone 3 parallel
17,65018,8702029-02-15
4FIT-1020 Interior fit-out — zone 314,08022,9502029-02-14
5FIT-1030 Interior fit-out — zone 4210,20033,1502029-02-12
6FIT-1030 Interior fit-out — zone 4
FIT-1040 Interior fit-out — zone 5 parallel
35,61038,7602029-02-09
7FIT-1040 Interior fit-out — zone 515,10043,8602029-02-08
8FIT-1040 Interior fit-out — zone 5
FIT-1050 Interior fit-out — zone 6 parallel
17,14051,0002029-02-07
9FIT-1050 Interior fit-out — zone 6
FIT-1060 Interior fit-out — zone 7 parallel
16,12057,1202029-02-06
10FIT-1060 Interior fit-out — zone 7
FIT-1070 Interior fit-out — zone 8 parallel
17,65064,7702029-02-05
11FIT-1070 Interior fit-out — zone 834,08068,8502029-02-02
12FIT-1080 Interior fit-out — zone 9210,20079,0502029-01-31
13FIT-1080 Interior fit-out — zone 9
FIT-1090 Interior fit-out — zone 10 parallel
15,61084,6602029-01-30
14FIT-1090 Interior fit-out — zone 1015,10089,7602029-01-29
15FIT-1090 Interior fit-out — zone 10
FIT-1100 Interior fit-out — zone 11 parallel
37,14096,9002029-01-26
16FIT-1100 Interior fit-out — zone 11
FIT-1110 Interior fit-out — zone 12 parallel
16,120103,0202029-01-25
17FIT-1110 Interior fit-out — zone 12
FIT-1120 Interior fit-out — zone 13 parallel
17,650110,6702029-01-24
18FIT-1120 Interior fit-out — zone 1314,080114,7502029-01-23
19FIT-1130 Interior fit-out — zone 14410,200124,9502029-01-19
20FIT-1130 Interior fit-out — zone 14
FIT-1140 Interior fit-out — zone 15 parallel
15,610130,5602029-01-18
21FIT-1140 Interior fit-out — zone 1515,100135,6602029-01-17
22FIT-1140 Interior fit-out — zone 15
FIT-1150 Interior fit-out — zone 16 parallel
17,140142,8002029-01-16
23FIT-1150 Interior fit-out — zone 16
FIT-1160 Interior fit-out — zone 17 parallel
16,120148,9202029-01-15
24FIT-1160 Interior fit-out — zone 17
FIT-1170 Interior fit-out — zone 18 parallel
37,650156,5702029-01-12
25FIT-1170 Interior fit-out — zone 1814,080160,6502029-01-11
26FIT-1180 Interior fit-out — zone 19210,200170,8502029-01-09
27FIT-1180 Interior fit-out — zone 19
FIT-1190 Interior fit-out — zone 20 parallel
15,610176,4602029-01-08
28FIT-1190 Interior fit-out — zone 2035,100181,5602029-01-05
29FIT-1190 Interior fit-out — zone 20
FIT-1200 Interior fit-out — zone 21
POD-1000 Podium structure — zone 1
TWR-1000 Tower structure — zone 1 parallel
119,290200,8502029-01-04
30POD-1000 Podium structure — zone 1
TWR-1000 Tower structure — zone 1 parallel
112,150213,0002029-01-03
31POD-1000 Podium structure — zone 1
POD-1010 Podium structure — zone 2
TWR-1000 Tower structure — zone 1
TWR-1010 Tower structure — zone 2 parallel
113,365226,3652029-01-02
32POD-1010 Podium structure — zone 2
TWR-1010 Tower structure — zone 2 parallel
112,150238,5152029-01-01
33POD-1010 Podium structure — zone 2
POD-1020 Podium structure — zone 3
TWR-1010 Tower structure — zone 2
TWR-1020 Tower structure — zone 3 parallel
317,010255,5252028-12-29
34POD-1020 Podium structure — zone 3
TWR-1020 Tower structure — zone 3 parallel
220,655276,1802028-12-27
35POD-1030 Podium structure — zone 4
TWR-1030 Tower structure — zone 4 parallel
536,450312,6302028-12-22
36POD-1040 Podium structure — zone 5
TWR-1040 Tower structure — zone 5 parallel
336,450349,0802028-12-19
37POD-1040 Podium structure — zone 5
POD-1050 Podium structure — zone 6
TWR-1040 Tower structure — zone 5
TWR-1050 Tower structure — zone 6 parallel
115,795364,8752028-12-18
38POD-1050 Podium structure — zone 6
TWR-1050 Tower structure — zone 6 parallel
312,150377,0252028-12-15
39POD-1050 Podium structure — zone 6
POD-1060 Podium structure — zone 7
TWR-1050 Tower structure — zone 6
TWR-1060 Tower structure — zone 7 parallel
113,365390,3902028-12-14
40POD-1060 Podium structure — zone 7
TWR-1060 Tower structure — zone 7 parallel
112,150402,5402028-12-13
41POD-1060 Podium structure — zone 7
POD-1070 Podium structure — zone 8
TWR-1060 Tower structure — zone 7
TWR-1070 Tower structure — zone 8 parallel
117,010419,5502028-12-12
42POD-1070 Podium structure — zone 8
TWR-1070 Tower structure — zone 8 parallel
420,655440,2052028-12-08
43POD-1080 Podium structure — zone 9
TWR-1080 Tower structure — zone 9 parallel
336,450476,6552028-12-05
44POD-1090 Podium structure — zone 10
TWR-1090 Tower structure — zone 10 parallel
536,450513,1052028-11-30
45POD-1090 Podium structure — zone 10
POD-1100 Podium structure — zone 11
TWR-1090 Tower structure — zone 10
TWR-1100 Tower structure — zone 11 parallel
115,795528,9002028-11-29
46POD-1100 Podium structure — zone 11
TWR-1100 Tower structure — zone 11 parallel
112,150541,0502028-11-28
47POD-1100 Podium structure — zone 11
POD-1110 Podium structure — zone 12
TWR-1100 Tower structure — zone 11
TWR-1110 Tower structure — zone 12 parallel
113,365554,4152028-11-27
48POD-1110 Podium structure — zone 12
TWR-1110 Tower structure — zone 12 parallel
312,150566,5652028-11-24
49POD-1110 Podium structure — zone 12
POD-1120 Podium structure — zone 13
TWR-1110 Tower structure — zone 12
TWR-1120 Tower structure — zone 13 parallel
117,010583,5752028-11-23
50POD-1120 Podium structure — zone 13
TWR-1120 Tower structure — zone 13 parallel
220,655604,2302028-11-21
51POD-1130 Podium structure — zone 14
TWR-1130 Tower structure — zone 14 parallel
536,450640,6802028-11-16
52POD-1140 Podium structure — zone 15
TWR-1140 Tower structure — zone 15 parallel
336,450677,1302028-11-13
53POD-1140 Podium structure — zone 15
POD-1150 Podium structure — zone 16
TWR-1140 Tower structure — zone 15
TWR-1150 Tower structure — zone 16 parallel
315,795692,9252028-11-10
Rows marked parallel

These compress two or more critical chains in the same step. They must be actioned together: shortening only one of the named activities will not move the completion date, and the spend on it will not be recovered.

ScheduleInsight · Acceleration Plan5
4 · Cost-efficiency curve28 Feb 2026

04 Cost-efficiency curve

Cumulative spend runs left to right; days bought run top to bottom. A steep section is efficient spending — many days for little money. As the curve flattens, each further day costs more than the one before it, because the cheap compression has already been taken and what remains is dearer.

Cumulative spend against days bought
knee · 200,8500692,925 spent · 102d bought

The marked knee at 200,850 is where a day first costs more than twice the opening rate of 4,930 per day. Everything left of it is the efficient part of the plan.

ScheduleInsight · Acceleration Plan6
5 · Method and basis28 Feb 2026

05 Method, basis and limitations

What this report is. A least-cost compression analysis of the schedule file as provided, computed in the browser; the file was not uploaded. Dates come from a multi-calendar critical path calculation run in full after every compression step.

What it is not. Not a quotation, a commitment, or professional commercial advice. The costs are derived from two stated assumptions (see Basis and assumptions), not from any priced offer. Whether an activity can in fact be compressed — labour availability, procurement lead time, permitting, sequencing, contractual constraint — is a judgement the schedule file cannot make and this analysis does not attempt.

Before relying on it. Treat the ranking and the shape of the curve as the output; treat the cash figures as indicative until each named activity has been tested with the party who would have to deliver it.

Generated by ScheduleInsight · 02-Mar-2026 11:20. Primavera and P6 are trademarks of Oracle Corporation; Microsoft Project of Microsoft Corporation. ScheduleInsight is independent and not affiliated with or endorsed by them.

ScheduleInsight · Acceleration Plan7
Appendix A · Compression log28 Feb 2026

A Step-by-step compression log

The plan compresses in one-day increments so each move can be re-scheduled and verified before the next. Consecutive increments on the same activities are shown as one instruction in the plan; this is the full log behind it — 72 verified steps.

#CompressedDaysCostFinish
1FIT-100015,1002029-02-19
2FIT-1000 + FIT-101036,1202029-02-16
3FIT-1010 + FIT-102017,6502029-02-15
4FIT-102014,0802029-02-14
5FIT-103015,1002029-02-13
6FIT-103015,1002029-02-12
7FIT-1030 + FIT-104035,6102029-02-09
8FIT-104015,1002029-02-08
9FIT-1040 + FIT-105017,1402029-02-07
10FIT-1050 + FIT-106016,1202029-02-06
11FIT-1060 + FIT-107017,6502029-02-05
12FIT-107034,0802029-02-02
13FIT-108015,1002029-02-01
14FIT-108015,1002029-01-31
15FIT-1080 + FIT-109015,6102029-01-30
16FIT-109015,1002029-01-29
17FIT-1090 + FIT-110037,1402029-01-26
18FIT-1100 + FIT-111016,1202029-01-25
19FIT-1110 + FIT-112017,6502029-01-24
20FIT-112014,0802029-01-23
21FIT-113015,1002029-01-22
22FIT-113035,1002029-01-19
23FIT-1130 + FIT-114015,6102029-01-18
24FIT-114015,1002029-01-17
25FIT-1140 + FIT-115017,1402029-01-16
26FIT-1150 + FIT-116016,1202029-01-15
27FIT-1160 + FIT-117037,6502029-01-12
28FIT-117014,0802029-01-11
29FIT-118015,1002029-01-10
30FIT-118015,1002029-01-09
31FIT-1180 + FIT-119015,6102029-01-08
32FIT-119035,1002029-01-05
33FIT-1190 + FIT-1200 + POD-1000 + TWR-1000119,2902029-01-04
34POD-1000 + TWR-1000112,1502029-01-03
35POD-1000 + POD-1010 + TWR-1000 + TWR-1010113,3652029-01-02
36POD-1010 + TWR-1010112,1502029-01-01
37POD-1010 + POD-1020 + TWR-1010 + TWR-1020317,0102028-12-29
38POD-1020 + TWR-1020112,1502028-12-28
39POD-1020 + TWR-102018,5052028-12-27
40POD-1030 + TWR-1030112,1502028-12-26
41POD-1030 + TWR-1030112,1502028-12-25
42POD-1030 + TWR-1030312,1502028-12-22
43POD-1040 + TWR-1040112,1502028-12-21
44POD-1040 + TWR-1040112,1502028-12-20
45POD-1040 + TWR-1040112,1502028-12-19
46POD-1040 + POD-1050 + TWR-1040 + TWR-1050115,7952028-12-18
47POD-1050 + TWR-1050312,1502028-12-15
48POD-1050 + POD-1060 + TWR-1050 + TWR-1060113,3652028-12-14
49POD-1060 + TWR-1060112,1502028-12-13
50POD-1060 + POD-1070 + TWR-1060 + TWR-1070117,0102028-12-12
51POD-1070 + TWR-1070112,1502028-12-11
52POD-1070 + TWR-107038,5052028-12-08
53POD-1080 + TWR-1080112,1502028-12-07
54POD-1080 + TWR-1080112,1502028-12-06
55POD-1080 + TWR-1080112,1502028-12-05
56POD-1090 + TWR-1090112,1502028-12-04
57POD-1090 + TWR-1090312,1502028-12-01
58POD-1090 + TWR-1090112,1502028-11-30
59POD-1090 + POD-1100 + TWR-1090 + TWR-1100115,7952028-11-29
60POD-1100 + TWR-1100112,1502028-11-28
61POD-1100 + POD-1110 + TWR-1100 + TWR-1110113,3652028-11-27
62POD-1110 + TWR-1110312,1502028-11-24
63POD-1110 + POD-1120 + TWR-1110 + TWR-1120117,0102028-11-23
64POD-1120 + TWR-1120112,1502028-11-22
65POD-1120 + TWR-112018,5052028-11-21
66POD-1130 + TWR-1130112,1502028-11-20
67POD-1130 + TWR-1130312,1502028-11-17
68POD-1130 + TWR-1130112,1502028-11-16
69POD-1140 + TWR-1140112,1502028-11-15
70POD-1140 + TWR-1140112,1502028-11-14
71POD-1140 + TWR-1140112,1502028-11-13
72POD-1140 + POD-1150 + TWR-1140 + TWR-1150315,7952028-11-10
ScheduleInsight · Acceleration Plan8