ScheduleInsight · Baseline Comparison

Tower C — Commercial Tower & Podium

Programme R12 update vs R10 approved baseline
Delay & variance report

NET CRITICAL SLIP
3 DELAY EVENTS · 36d GROSS · 18d ABSORBED
+18dto completion
Client
Meridian Estates (owner)
Contractor
Calderwood Construction Ltd
Contract
JCT D&B 2016
Baseline
R10 — approved 30 Nov 2025
Update
R12 — data date 28 Feb 2026
Activities
3,842 (2,970 matched)
Baseline finish
1 November 2027
Current finish
19 November 2027
Report reference
SI-BC-EX-002
ScheduleInsight
Parsed on-device · file never uploaded
Tower C · R12 vs R10 · Baseline Comparison28 Feb 2026

Contents

Report
01Delay summary3
02How the finish date moved4
03What changed in the critical path5
04Basis, matching and limitations6
Appendices — supporting detail
AVariance register7
BCritical-path change8
CMatching basis and provenance9
How to read this report

Section 1 states the movement and the one distinction that governs the whole report: gross delay is 36 days, net movement of the completion date is 18. Sections 2 and 3 show how one becomes the other, and what changed in the critical path along the way.

Appendix A lists every varied activity, Appendix B the critical-path change activity by activity, and Appendix C the matching basis — which activities were compared, and which could not be.

ScheduleInsight · Baseline Comparison2
1 · Delay summary28 Feb 2026

01 Delay summary

Completion has moved from 1 November 2027 to 19 November 2027 — a net critical slip of 18 days against the approved baseline. Three distinct delay events lie on or join the critical path this period.

Baseline finish (R10)
1 Nov 2027

Contract completion per the approved baseline of record.

Current forecast (R12)
19 Nov 2027

Forecast completion per the current update.

Gross and net are different numbers — both are true

Delay events total 36 days. The completion date moved 18. The difference is not an error and it is not mitigation alone: 18 days were absorbed, partly by float on non-driving paths and partly by declared acceleration. Quoting 36 overstates the position; quoting 18 conceals how much had to be spent to hold it there.

+18d contractor risk
+12d employer risk
+6d disclosure
−18d recovered
Contractor Employer Disclosure Absorbed / recovered

Float is no longer available to absorb the next event

Holding the position at +18 days consumed effectively all of the remaining path float. Seventeen activities now sit in negative float where the baseline had none. The practical consequence is that the next disruption of any size lands directly on the completion date, because there is nothing left between it and completion.

ScheduleInsight · Baseline Comparison3
2 · Delay waterfall28 Feb 2026

02 How the finish date moved

The bridge from the baseline finish to the current forecast, in critical-path calendar days. Each bar is a movement that reached the completion date; movements absorbed by float do not appear here and are listed in Appendix A.

Figure 1 — Baseline finish to current forecast
+40d +30d +20d +10d 0d R10 baseline 1 Nov 27 +18 Grid G steel resequence +12 Pre-pour hold design query +6 MEP logic gap −11 Cladding resequence −7 Fabrication acceleration Net +18d → 19 Nov 27
Two additive events and one recovery. The +18 day Grid G rework is the largest single movement and is contractor risk; the +12 day pre-pour hold is employer risk and runs partly concurrent with it. The −18 day recovery is declared acceleration, not float. Every figure is traced to activities in Appendix B.

Why the arithmetic does not simply add up

+18 and +12 against −18 would give +12, not the +18 observed. The residual six days arise where the two delay events overlap: during the concurrency the recovery cannot be applied twice, so acceleration bought back calendar time on only one of the two paths. This is the normal behaviour of a network under concurrent delay and it is why the movement must be taken from the recalculated critical path rather than from a sum of event durations.

ScheduleInsight · Baseline Comparison4
3 · Critical path28 Feb 2026

03 What changed in the critical path

The driving path to completion is not the same chain it was at baseline. One activity has entered it and the sequence beyond that point has re-ordered.

R10 baseline path

A1390 Steel delivery
A1422 Grid G columns
A1560 Deck L4–6
A1801 MEP rough-in
A2240 Core handover

R12 current path

A1390 Steel delivery−6d
A1422 Grid G columns+18d
A1733 Pre-pour hold NEW+12d
A1801 MEP rough-in+6d
A2240 Core handovershifted
A1733 was not on the baseline critical path

The Level 3 pre-pour hold has entered the driving path this period. An activity that was not critical at baseline and is critical now is the clearest signal available that the plan's assumptions have changed — it means float that the baseline relied on has been consumed elsewhere, and A1560 (Deck L4–6) has correspondingly dropped off the path.

The re-ordering matters for management as much as for measurement: mitigation aimed at the baseline critical path would now be aimed at the wrong activities. Any acceleration proposed from here should be tested against the R12 path, not the approved one.

ScheduleInsight · Baseline Comparison5
4 · Basis28 Feb 2026

04 Basis, matching and limitations

This report compares two Primavera P6 files activity by activity. Everything in it derives from that comparison; nothing is asserted from outside the two files.

What was compared

Limitations

Illustrative example

Produced from fictional project data for illustration. No real schedule, client or contractor data is used or implied.

ScheduleInsight · Baseline Comparison6
Appendix A · Variance register28 Feb 2026

A Variance register — activities that moved

Every matched activity whose dates changed by more than two days, ordered by impact on completion. “Critical” indicates the activity lies on the R12 driving path.

ActivityDescriptionBaseline finishCurrent finishVarFloatCrit
A1422Erect columns Grid G, L4–614 Jul 271 Aug 27+18d−18dYes
A1733Level 3 pre-pour inspection02 Aug 2714 Aug 27+12d−12dYes
A1801MEP rough-in Zone A18 Aug 2724 Aug 27+6d−6dYes
A1560Metal deck & concrete L4–628 Jul 2730 Jul 27+2d4dNo
A2110Curtain wall North — accelerated22 Sep 2710 Sep 27−12d0dYes
A1390Steel delivery release 2 — extra shift28 Jun 2722 Jun 27−6d0dYes
A2240Core handover01 Nov 2719 Nov 27+18d−18dYes
Net movement of the driving path to completion+18d

Movements absorbed by float

Fourteen further activities moved by more than two days without affecting completion. Together they account for the difference between 36 days of gross event duration and 18 days of net movement.

RangeActivitiesTotal movementEffect on completion
Moved, float remaining11+31dNone — absorbed
Moved, float exhausted3+9dPartial — see Appendix B
ScheduleInsight · Baseline Comparison7
Appendix B · Critical path28 Feb 2026

B Critical-path change, activity by activity

The driving path in each revision, in sequence. Activities present in one path only are the structural change; activities present in both may still have moved.

SeqR10 baseline pathR12 current pathChange
1A1390 Steel deliveryA1390 Steel delivery−6d
2A1422 Grid G columnsA1422 Grid G columns+18d
3A1560 Deck L4–6A1733 Pre-pour holdReplaced
4A1801 MEP rough-inA1801 MEP rough-in+6d
5A2240 Core handoverA2240 Core handoverShifted

Float profile, baseline versus current

Float bandR10 baselineR12 currentChange
Negative float017+17
Zero float (critical)4258+16
1 – 20 days311402+91
Over 20 days2,6172,493−124

The whole distribution has shifted left. This is the numeric form of the finding in section 1: the programme has less room than it had, everywhere, not only on the driving path.

ScheduleInsight · Baseline Comparison8
Appendix C · Matching28 Feb 2026

C Matching basis, unmatched activities and provenance

Comparison is by activity ID. An activity present in one revision only cannot be varianced, and is reported here rather than silently excluded.

CategoryCountTreatment in this report
Matched on activity ID2,970Varianced — Appendix A
Added in R12604No baseline to compare; listed below where critical
Removed since R10211Reported as scope change, not as variance
Likely renumbered57Flagged by name similarity; pairing not asserted
Total activities in R123,842

Added activities on or near the driving path

ActivityDescriptionDurationFloat
A1733Level 3 pre-pour inspection — added R1112d−12d
A2115Curtain wall acceleration works — added R1218d0d

Both additions are consequences of events described in section 2 rather than scope growth. A1733 formalises a hold that was previously untracked; A2115 is the declared acceleration.

Baseline file
TowerC_R10_2025-11-30.xer
Update file
TowerC_R12_2026-02-28.xer
Baseline finish
2027-11-01
Current finish
2027-11-19
Matched
2,970 / 3,842
Report reference
SI-BC-EX-002
ScheduleInsight · Baseline Comparison9