ScheduleInsight · CE Programme Impact

Ganymede FPSO — Topside Modifications

CE-014 — revised flare knock-out drum tie-in
Accepted Programme AP-06 → impacted programme · NEC3 ECC Option A

PLANNED COMPLETION MOVES
+9 DAYS — 28 JAN 2025 → 6 FEB 2025
+9days
Client
TerraOcean Energy Ltd
Contractor
Apex Marine & Engineering Ltd
Contract
NEC3 ECC Option A
Event reference
CE-014
Dividing date
3 October 2024
Accepted Programme
AP-06 — accepted 22 Aug 2024
Impacted programme
AP-06 + CE-014
Assessment date
15 October 2024
Report reference
SI-CE-EX-007
ScheduleInsight
Parsed on-device · file never uploaded
Ganymede FPSO · CE-014 · Programme Impact15 Oct 2024

Contents

Report
01Time effect on planned Completion3
02Basis of assessment4
03The driving path5
04What this does not decide6
Appendices — supporting detail
ADriving path — full register7
BKey Dates and milestones8
CProgramme provenance9
How to read this report

Section 1 is the time effect and the measurement that produces it. Section 2 sets out the basis — which two programmes were compared, at which date, and why the movement of planned Completion is the measure the contract asks for. Section 3 walks the driving path so the movement can be traced to activities rather than accepted as a total.

Appendix A is the driving path activity by activity; Appendix B records the Key Dates and milestones and how each moved; Appendix C records the provenance of both programmes. Section 4 states what this assessment does not decide, which on a compensation event is as important as what it does.

ScheduleInsight · CE Programme Impact2
1 · Time effect15 Oct 2024

01 Time effect on planned Completion

+9
DAYS
PLANNED
COMPLETION

CE-014 delays planned Completion by 9 days, from 28 January 2025 to 6 February 2025.

The movement is measured between the Accepted Programme current at the dividing date (AP-06) and the same programme impacted by the event. Both are run on identical calendars and identical logic; the only difference between them is CE-014.

Accepted
28 Jan 2025
Impacted
6 Feb 2025
Movement
+9 days

How the 9 days arise

Tie-in redesign & approval+14d
Absorbed by float on the KO drum path−5d
Net effect on planned Completion+9d

The event adds 14 days to the flare knock-out drum tie-in chain. Five of those days are absorbed by the total float that path carried at the dividing date, and the remaining 9 days pass through to planned Completion. The float consumed belonged to the Contractor under the ECC; its consumption is reported here because it explains the difference between the event's duration and its effect, not because it is itself a matter for assessment.

Prospective, on the programme as accepted

This is a prospective assessment: it asks what the event does to the programme, not what has since happened on site. That is the basis the ECC requires for a compensation event, and it is why the answer does not change if the works later run early or late for unrelated reasons. Actual progress after the dividing date is deliberately excluded — including it would convert a forecast into a retrospective claim and quietly change the question being answered.

ScheduleInsight · CE Programme Impact3
2 · Basis15 Oct 2024

02 Basis of assessment

The two programmes compared

The assessment compares AP-06, the Accepted Programme current at the dividing date of 3 October 2024, with that same programme impacted by CE-014 and re-run. No other change was made between the two: the calendars, the resource assignments, the constraint set and every activity unaffected by the event are identical. A difference in planned Completion between the two can therefore only be attributable to the event.

Why the movement of planned Completion is the measure

Under the ECC, the delay to the Completion Date is assessed as the delay to planned Completion shown on the Accepted Programme (clause 63.3 under NEC3). The measure is deliberately not "the delay on site" and not "the delay to the Completion Date as previously assessed": it is the movement of the Contractor's own planned Completion when the event is applied to the programme that was accepted. That is what has been measured here.

The dividing date and why it matters

The dividing date of 3 October 2024 is the date of the Project Manager's instruction giving rise to the event. Work before it is treated as fact; work after it is treated as forecast. Choosing a later programme revision would fold in delays that arose after the event and are not caused by it; choosing an earlier one would ignore accepted changes that were properly part of the plan when the event occurred. AP-06 is the revision in force on that date.

Float ownership under the ECC

Total float belongs to the Contractor and is available to absorb the effect of an event before planned Completion moves. That is why 5 of the 14 days disappear in section 1 without any entitlement arising from them. Terminal float — time between planned Completion and the Completion Date — is treated differently and is not present on this programme; had it been, it would be reported separately rather than netted off silently.

Both programmes were parsed on-device from the files listed at Appendix C. Neither file was uploaded and no copy is retained.

ScheduleInsight · CE Programme Impact4
3 · Driving path15 Oct 2024

03 The driving path

The 9 days reach planned Completion along a single path. Six activities moved; each is listed in full at Appendix A.

Where the delay travels

The instructed redesign holds A-2140 KO drum tie-in detail design, which in turn holds fabrication, delivery to the module, installation and the commissioning sequence that follows it. The path was already the driving path to planned Completion before the event; CE-014 lengthened it rather than changing which path drives, which is the simpler and more defensible of the two cases.

IDActivityAcceptedImpactedDelta
A-2140KO drum tie-in detail design18 Oct 2401 Nov 24+14d
A-2155Spool fabrication — tie-in pieces08 Nov 2422 Nov 24+14d
A-2170Delivery to module & receipt15 Nov 2429 Nov 24+14d
A-2210Tie-in installation & NDT06 Dec 2417 Dec 24+11d
A-2340Flare system pre-commissioning09 Jan 2518 Jan 25+9d
A-2400Planned Completion28 Jan 2506 Feb 25+9d

Why the delta shrinks along the path

The event adds 14 days at A-2140 but only 9 arrive at Completion. The reduction happens twice and is visible in the table: 3 days are absorbed at A-2210, where the installation window had float against the commissioning sequence, and 2 further days at A-2340. No days are lost to rounding or to calendar differences — both programmes use the same offshore calendar, and the arithmetic closes exactly at 14 − 5 = 9.

One path, this time

This event happens to lengthen the existing driving path. Where an event instead makes a different path critical, the movement of planned Completion is still the correct measure, but the driving path in the impacted programme will not match the accepted one and the two must be read side by side. Appendix A shows both paths in that case; here they are the same six activities.

ScheduleInsight · CE Programme Impact5
4 · Limits15 Oct 2024

04 What this does not decide

This report assesses one thing: the effect of CE-014 on planned Completion. Four questions that usually accompany it are outside its scope, and are listed here so that no reader has to infer the boundary.

Whether CE-014 is a compensation event

Not decided here. Whether the instruction falls within one of the events listed at clause 60.1, and whether it was notified in time under clause 61, are matters for the Project Manager and the Contractor under the contract. This report takes the event as given and measures its programme effect; if the event is later found not to be a compensation event, the measurement is simply not used.

The change to the Prices

Not assessed here. The change to Defined Cost plus Fee is a cost assessment requiring rates, resources and records that a programme file does not contain. The time effect established here is an input to that assessment — prolongation is priced against a period, and this is the period — but it is not itself a valuation. The quotation pack at SI-NQ-EX-008 carries the placeholder for the estimator.

Concurrency and other causes

Not allocated here. The comparison isolates CE-014 by holding everything else constant, which is the right way to measure one event but means the report is silent on whether another cause was operating over the same period. Where two events overlap, each will measure at its full effect in its own assessment and the two cannot simply be added. Resolving that is a matter for the Project Manager's assessment under clause 64.

Acceleration and mitigation

Not assumed. The impacted programme applies the event to the accepted logic without adding resource, re-sequencing or working additional shifts. If the Contractor is instructed to mitigate, or elects to, the effect changes and the assessment should be re-run on the mitigated programme rather than adjusted by judgement.

Assessment aid — not a determination

This report gives a prospective, programme-to-programme triage of a compensation event's effect on planned Completion, to support a Contractor's quotation under clause 62 or a Project Manager's assessment under clause 64. It does not decide entitlement, does not value the event, and does not allocate concurrency. The Project Manager and the Contractor remain responsible for the assessment under the contract, and for confirming every clause reference against the contract edition and main Option actually in use.

ScheduleInsight · CE Programme Impact6
Appendix A · Driving path15 Oct 2024

A Driving path — full register

Every activity on the driving path to planned Completion whose dates moved, in sequence. "Float at dividing date" is the total float each activity carried on AP-06 before the event was applied — it is what the reduction in delta along the path is spent from.

IDActivityAccepted finishImpacted finishDeltaFloat at DD
A-2140KO drum tie-in detail design18 Oct 2401 Nov 24+14d0d
A-2155Spool fabrication — tie-in pieces08 Nov 2422 Nov 24+14d0d
A-2170Delivery to module & receipt15 Nov 2429 Nov 24+14d0d
A-2210Tie-in installation & NDT06 Dec 2417 Dec 24+11d3d
A-2265Reinstatement & insulation20 Dec 2431 Dec 24+11d3d
A-2340Flare system pre-commissioning09 Jan 2518 Jan 25+9d2d
A-2380Flare cold commissioning22 Jan 2531 Jan 25+9d0d
A-2400Planned Completion28 Jan 2506 Feb 25+9d0d
Net effect on planned Completion28 Jan 2506 Feb 25+9d5d absorbed

The driving path is identical in both programmes, so a single register serves for each. Where an event changes which path drives, both paths are listed and the activities present in one only are marked.

ScheduleInsight · CE Programme Impact7
Appendix B · Key Dates15 Oct 2024

B Key Dates and milestones

Every Key Date and sectional milestone on the programme, with its movement under the event. Key Dates carry their own obligations under clause 30.3 and are assessed independently of Completion — a milestone can move without planned Completion moving, and the reverse.

IDKey Date / milestoneAcceptedImpactedMove
KD-01Topside module ready for hook-up04 Nov 2404 Nov 24nil
KD-02Power generation available29 Nov 2429 Nov 24nil
KD-03Flare system mechanically complete03 Jan 2514 Jan 25+11d
KD-04Process systems ready for commissioning16 Jan 2525 Jan 25+9d
MS-11Marine spread demobilised24 Jan 2524 Jan 25nil
MS-12Sectional handover — utilities20 Dec 2420 Dec 24nil
A-2400Planned Completion28 Jan 2506 Feb 25+9d

KD-03 moves further than Completion. The flare system Key Date sits on the affected path with less float than the path to Completion, so it absorbs less of the event: 11 days against 9. A Key Date moving by more than planned Completion is not an inconsistency — it is the ordinary consequence of different float on different paths — but it is the item most often missed, and it carries its own consequences under clause 30.3 independently of the Completion Date.

ScheduleInsight · CE Programme Impact8
Appendix C · Provenance15 Oct 2024

C Programme provenance

The provenance of both programmes, recorded at the time of assessment so that the comparison can be reproduced exactly.

ItemAccepted ProgrammeImpacted programme
ReferenceAP-06AP-06 + CE-014
FileGanymede_AP06.xerGanymede_AP06_CE014.xer
FormatPrimavera P6 XERPrimavera P6 XER
StatusAccepted 22 August 2024Impacted for assessment only
Data date3 October 20243 October 2024
Activities1,8471,849
CalendarOffshore 14/14, 12hOffshore 14/14, 12h
Planned Completion28 January 20256 February 2025

Difference between the two files

The impacted programme contains two activities not present in AP-06A-2141 revised detail design cycle and A-2142 Project Manager review of revised detail — both being the instructed work itself. No activity was deleted, no duration outside the event was altered, no constraint was added or removed, and no calendar was changed. That list is exhaustive: any other difference between the two files would invalidate the comparison, so it is stated rather than summarised.

Assessment parameterValue
BasisProspective, programme-to-programme
Dividing date3 October 2024 — PM instruction
Clause appliedNEC3 ECC clause 63.3
Progress after dividing dateExcluded by design
Mitigation assumedNone
Assessment date15 October 2024
ProcessingOn-device — files not uploaded, not retained
ScheduleInsight · CE Programme Impact9