ScheduleInsight Example report ← All examples Pricing Analyse your schedule free
ScheduleInsight · Submission Report

Tower C — Commercial Tower & Podium

Programme R12 — acceptance gate
Owner / PMO acceptance decision · JCT D&B 2016

ACCEPT WITH COMMENTS
3 FAILED · 4 WARNINGS · 11 PASSED — 3 CONDITIONS APPLY
73/ 100
Prepared for
Meridian Estates — Owner's PMO
Submitted by
Calderwood Construction Ltd
Contract
JCT D&B 2016
Submission
Programme R12
Data date
28 February 2026
Acceptance rule
SQS ≥ 65 · ≤ 1 fail · ≤ 4 warn
Measured
73 · 3 fails · 4 warnings
Decision
Accept with comments
Report reference
SI-SR-EX-006
ScheduleInsight
Parsed on-device · file never uploaded
Tower C · Programme R12 · Submission Report28 Feb 2026

Contents

Report
01Acceptance decision3
02Conditions of acceptance4
03Watch-items for the next cycle5
04The rule, its basis and its limits6
Appendices — supporting detail
AFull 18-check gate register7
BAcceptance rule and provenance8
How to read this report

Section 1 is the decision and the arithmetic behind it — the rule applied, the values measured, and which term of the rule the submission failed. Section 2 states the conditions of acceptance: the three failures that must be corrected in R13. Section 3 records the watch-items that do not block acceptance but will if they persist.

Appendix A is the full 18-check gate register — every check, its measured value, the target applied and the result, so the contractor can reproduce the decision rather than take it on trust. Appendix B records the acceptance rule as configured, and the provenance of the file assessed.

ScheduleInsight · Submission Report2
1 · Decision28 Feb 2026

01 Acceptance decision

ACCEPT
WITH
COMMENTS
3 CONDITIONS
APPLY

Programme R12 is accepted with comments. It is broadly sound and fit to be worked to, but it carries three failed checks that must be corrected at the next revision.

The submission passes the score term of the acceptance rule comfortably — 73 against a required 65 — and passes the warning term exactly. It fails on one term only: three failed checks against a permitted one. That single failure is what separates this decision from a clean acceptance, and section 2 states what has to change.

The rule, and what was measured against it

Term of the acceptance ruleRequiredMeasuredResult
Schedule Quality Score≥ 6573PASS
Failed checks≤ 13FAIL
Warnings≤ 44PASS
Passed
11
Warnings
4
Failed
3
Passed — 11
Warn — 4
Failed — 3
Meets the target Watch-item Condition of acceptance
Why not a clean acceptance

Two of the three failures — 17 activities carrying negative float and 6 leads — mean the programme cannot be read at face value: negative float says the arithmetic already does not close, and leads let successors start before their predecessors finish. Accepting without conditions would put the owner's name to dates that the network itself does not support. The comments are the mechanism for accepting the programme as a working document while keeping that reservation on the record.

ScheduleInsight · Submission Report3
2 · Conditions28 Feb 2026

02 Conditions of acceptance

Three checks failed. Each is a condition of this acceptance and is to be corrected in R13.

Condition 1 — Negative float  17 activities · target zero

What it means. Seventeen activities carry total float below zero, which is the network reporting that it cannot achieve a date it has been told to achieve. Negative float is not a delay in itself; it is the symptom of a constraint or a logic path that contradicts the rest of the programme.

What to do. Trace each of the seventeen to its driver — in this programme they resolve to the hard constraints at check 14 — and either relax the constraint, re-sequence the path, or accept the date change and reforecast. Do not suppress the symptom by extending durations elsewhere.

Condition 2 — Leads (negative lags)  6 links · target zero

What it means. Six logic links carry a negative lag, allowing a successor to begin before its predecessor finishes. A lead is a shortcut around logic that has not been modelled: the real overlap may be legitimate, but the programme does not show what it is.

What to do. Replace each lead with the relationship it stands for — usually a start-to-start link with a positive lag, or a split of the predecessor into the portion that actually has to finish first. Six links is a contained correction and should not survive into R13.

Condition 3 — Hard constraints  3.1% · target < 2%

What it means. Mandatory-start and mandatory-finish constraints override logic: a constrained activity holds its date whatever its predecessors do, which is what produces the negative float at condition 1. At 3.1% the programme is materially constraint-driven rather than logic-driven.

What to do. Reduce to below 2% by removing constraints that duplicate contractual dates already modelled as milestones, and retaining only those the contract genuinely imposes. Where a hard constraint must stay, record why in the schedule basis so the next reviewer does not re-open it.

The three are one problem seen three ways

Conditions 1 and 3 are cause and effect: the hard constraints produce the negative float. Correcting the constraints should clear the majority of the seventeen negative-float activities without any other change. Condition 2 is independent and is the smaller job. A single focused revision should close all three.

ScheduleInsight · Submission Report4
3 · Watch-items28 Feb 2026

03 Watch-items for the next cycle

Four checks returned warnings. Under the configured rule they do not prevent acceptance — the submission is at the limit of four, not over it — but a fifth warning at R13 would.

Missing logic
5.0%

Target <5%. Sitting exactly on the threshold — no headroom at R13.

Out of sequence
11

Target zero. Work progressing against the logic as modelled.

CPLI
0.94

Target ≥1.0. The critical path is shorter than the time available to it.

BEI · SPI
0.91 · 0.93

Both target ≥1.0. Execution and progress agree: no recovery yet.

Where the margin actually is

Missing logic sits exactly on the threshold at 5.0%. This is the warning most likely to become a failure: a single revision that adds activities without adding their logic will cross it. It is recorded here so that the contractor knows there is no headroom, not because the current figure is objectionable.

Eleven out-of-sequence activities indicate work progressing against the logic as modelled. Each one is either a real change in method — in which case the logic should follow it — or a progress-reporting error. Both are corrections; neither is a delay.

CPLI 0.94, BEI 0.91, SPI 0.93. All three performance indices sit below unity and agree with one another, which is the more reliable signal: the programme is not currently recovering, and the critical path has less length available than it needs. These are the indices to watch across R13 and R14 rather than to act on in a single revision.

What would change the decision at R13

Clearing the three conditions moves the submission to a clean ACCEPT provided the warning count does not rise above four. Leaving any one condition unresolved holds it at ACCEPT WITH COMMENTS at best; a fall in score below 65, or a fourth failure, would put it into REJECT. The rule is applied identically at every revision, so the contractor can predict the outcome before submitting.

ScheduleInsight · Submission Report5
4 · Basis28 Feb 2026

04 The rule, its basis and its limits

What the gate is

The acceptance gate applies the organisation's configured acceptance rule to the 18-point schedule-quality assessment — the DCMA 14-point checks plus four supplementary indices — and returns one of three outcomes. ACCEPT where every term of the rule is met. ACCEPT WITH COMMENTS where the score is within ten points of the minimum and the failures are within two of the permitted number. REJECT otherwise. The bands are fixed; the thresholds are not.

Why the thresholds are configurable

The minimum score, the maximum failed checks and the maximum warnings are set per organisation, because an acceptance standard is a commercial position rather than a technical constant. A framework owner running many small works packages and a single-project client on a complex build should not be held to the same number, and a generic threshold applied to both would be arbitrary in one of the two cases. The rule applied to this submission is recorded in full at Appendix B so that the decision can be audited against the standard in force on the day it was made.

Applied consistently, or not at all

The value of a gate is that it is the same gate every time. Because the rule is stated numerically and evaluated mechanically, the same programme submitted twice returns the same verdict, and two contractors submitting comparable programmes are held to one standard. Where the reviewer disagrees with an outcome, the disagreement is with the rule — which can be changed deliberately and for the future — rather than with an individual judgement made once and unrecorded.

Decision support, not certification

This scorecard measures the structural quality of the programme as a network. It does not read the Works Information, does not verify that the scope is complete, does not confirm that durations are achievable, and does not check that the sequence is buildable. A programme can pass every check and still be wrong about the project. The verdict is an aid to the acceptance decision under the contract; the reviewing party remains responsible for accepting, conditionally accepting or rejecting the submission, and for the consequences of that decision.

Assessment performed on-device against Programme R12 as submitted. No file was uploaded and no copy is retained — see Appendix B for the file provenance recorded at the time of assessment.

ScheduleInsight · Submission Report6
Appendix A · Gate register28 Feb 2026

A Full 18-check gate register

Every check with its measured value, the target applied and the result. Checks 1–14 are the DCMA 14-point assessment; 15–18 are the supplementary indices. The three checks marked FAIL are the conditions of acceptance at section 2.

#CheckValueTargetResult
1Missing logic (open ends)5.0%<5%WARN
2Logic density2.52.0–3.5PASS
3Finish-to-start relationships86%>80%PASS
4Lags3.1%<5%PASS
5Leads (negative lags)6ZeroFAIL
6Out of sequence11ZeroWARN
7Negative float17ZeroFAIL
8Near-critical (float ≤ 10d)8.2%<10%PASS
9High float (> 44d)9.4%<10%PASS
10Critical path percentage12%<15%PASS
11CPLI0.94≥1.0WARN
12High duration (> 44d)4.2%<5%PASS
13Insufficient detail3.8%<5%PASS
14Hard constraints3.1%<2%FAIL
15Soft constraints4.4%<5%PASS
16Milestone coverage2.6%>2%PASS
17BEI (baseline execution index)0.91≥1.0WARN
18SPI (schedule performance index)0.93≥1.0WARN
Weighted Schedule Quality Score73≥ 65PASS

The score is a weighted composite, not the proportion of checks passed — which is why 11 passes out of 18 returns 73 rather than 61. The weighting is published on the methodology page and is identical for every schedule assessed.

ScheduleInsight · Submission Report7
Appendix B · Rule and provenance28 Feb 2026

B Acceptance rule and provenance

The acceptance rule as configured at the time of assessment, and the provenance of the file assessed. Both are recorded so the decision can be reproduced later against the standard actually in force, rather than against whatever the standard has since become.

Acceptance rule in force

ParameterValueEffect on the verdict
Minimum Schedule Quality Score65Below 65 the submission cannot be accepted; below 55 it is rejected outright.
Maximum failed checks1More than 1 blocks clean acceptance; more than 3 forces rejection.
Maximum warnings4More than 4 blocks clean acceptance.
Comments band−10 / +2Fixed. Score within 10 of the minimum and failures within 2 of the maximum returns ACCEPT WITH COMMENTS.

Thresholds are set on the Criteria tab and apply to every submission assessed by the organisation until changed. This submission was measured at 73 · 3 fails · 4 warnings, meeting the first and third terms and failing the second.

File and assessment provenance

ItemRecorded value
Submitted fileTowerC_R12.xer
FormatPrimavera P6 XER
Data date28 February 2026
Activities assessed3,842
Logic links assessed9,610
Baseline attachedR10 — approved 30 November 2025
Assessment date28 February 2026
Assessed byMeridian Estates — Owner's PMO
ProcessingOn-device — file not uploaded, not retained

Activity and link counts are those read from the submitted file, not from any prior revision. Where a count differs from the contractor's own figure the difference is usually filtered or excluded activities; the assessment reads every activity present in the file.

ScheduleInsight · Submission Report8

Run this gate on your own submissions.

Every report in the set is built from a Primavera P6 or Microsoft Project file, parsed in your browser. Nothing is uploaded and nothing is retained.