A complete Schedule Quality report on a real-format Primavera P6 programme — the DCMA 14-point assessment plus four further checks, scored 0–100, with the failing checks explained, the activities behind them named, and a plain-language narrative you can put in front of a client.

The eight pages below are the actual deliverable, not a preview of one. Print it and you get eight A4 sheets. Your schedule never leaves your browser — the file is parsed on your device and nothing is retained.

8 pages · A4 print-ready 18 checks · DCMA-aligned Thresholds configurable per organisation Self-contained HTML + PDF Parsed on-device Fictional data — illustrative example
ScheduleInsight · Schedule Quality Report

Tower C — Commercial Tower & Podium

Programme R12 · schedule quality assessment
18 checks — DCMA 14-point plus four

BELOW HEALTHY THRESHOLD
3 FAILED · 4 WARNINGS · 11 PASSED
73/ 100
Prepared for
PMO / Owner's representative
Data date
28 February 2026
Forecast finish
19 November 2027
Baseline
R10 — attached
Activities
3,842
Logic links
9,610
Healthy threshold
75 / 100
Movement vs R10
−4 points
Report reference
SI-SQ-EX-000
ScheduleInsight
Parsed on-device · file never uploaded
Tower C · Programme R12 · Schedule Quality28 Feb 2026

Contents

Report
01Score and what it means3
02The checks that need action4
03Critical findings5
04Narrative and basis6
Appendices — supporting detail
AFull 18-check register7
BMovement and provenance8
How to read this report

Section 1 is the score and what it means. Section 2 explains the three checks that failed and the four that warned — these are the only checks that require action. Section 3 names the activities behind them and section 4 is the narrative for circulation.

Appendix A is the full 18-check register with every value, target and result, and Appendix B the provenance. A passing check needs no explanation in the body, so it lives in the register.

ScheduleInsight · Schedule Quality Report2
1 · Score28 Feb 2026

01 Score and what it means

The programme scores 73 out of 100, four points below the previous revision and under the 75 threshold we treat as healthy. Eleven of the eighteen checks pass, four warn and three fail.

Schedule Quality Score
73 / 100

Weighted across 18 checks. Healthy threshold 75; R10 baseline scored 77.

Check outcomes
11 / 4 / 3

Passed, warned and failed. The three failures carry most of the deduction.

11 passed
4 warn
3 failed
Pass Warn Fail

What the score measures

Schedule quality is a measure of how trustworthy the programme is — whether the dates it produces can be relied on. It says nothing about whether the project is going well; a badly performing project can have an excellent programme, and a well performing one can have a programme nobody should believe. At 73 this network is broadly sound: the logic is mostly complete and the critical path is credible.

Where the four points went

The decline is concentrated in the structural steel scope. Negative float rose from 4 activities to 17, and hard constraints from 1.4% to 2.6%. Both are symptoms of the same thing: dates being held in place by constraint rather than by logic once the sequence came under pressure.

ScheduleInsight · Schedule Quality Report3
2 · Failures and warnings28 Feb 2026

02 The checks that need action

Eleven checks pass and need no comment; they are recorded in Appendix A. The seven below are the whole of the actionable content.

Failed — three checks

#CheckValueTargetWhat it means here
7Negative float17ZeroSeventeen activities cannot be completed by their required dates as logic stands
14Hard constraints3.1%<2%Dates pinned by constraint rather than logic; masks true float
5Leads (negative lags)6ZeroSix links pull a successor earlier than its predecessor finishes

Warned — four checks

#CheckValueTargetWhat it means here
1Missing logic (open ends)5.0%<5%Exactly on the boundary — concentrated in the MEP rough-in chain
6Out of sequence11ZeroProgress recorded against logic that says it could not have happened yet
11CPLI0.94≥1.0The critical path is 6% longer than the time available
17BEI0.91≥1.0Activities are completing at 91% of the baseline rate
The three failures are one problem, not three

Negative float, hard constraints and negative lags all appear in the same scope and in the same revision. When a sequence comes under pressure and the dates are held rather than re-planned, this is the signature it leaves. Fixing the constraints will reveal more negative float before it reduces it, and that is the correct direction of travel.

ScheduleInsight · Schedule Quality Report4
3 · Critical findings28 Feb 2026

03 Critical findings

The activities driving the score, ordered by slip against the R10 baseline. Each is named so the finding can be acted on rather than merely noted.

ActivityNameIssueBaselineCurrentSlip
A1422Erect columns Grid G, L4–6Negative float10 Jul 2728 Jul 27+18d
A1733Pre-pour inspection, Level 3Hard constraint02 Aug 2714 Aug 27+12d
A1801MEP rough-in, Zone AOpen end19 Aug 2726 Aug 27+7d
A2104Curtain wall install, NorthNegative lag03 Sep 2709 Sep 27+6d
A2240Lift core handoverOut of sequence21 Sep 2725 Sep 27+4d

What to fix first

Every threshold above is configurable per organisation. Where your standard differs from the DCMA default, the score recalculates against yours.

ScheduleInsight · Schedule Quality Report5
4 · Narrative28 Feb 2026

04 Narrative and basis

Written for circulation. Every figure in it is traced to an activity in section 3 or a check in Appendix A.

The programme scores 73/100, four points below the previous revision and under the 75 healthy threshold. The decline is concentrated in the structural steel scope, where 17 activities now carry negative float — most critically A1422, Erect columns Grid G, which has slipped 18 days against the R10 baseline and is driving the longest path.

Three activities have been re-anchored with hard constraints, above the 2% target. Constraints of this kind mask true float and should be replaced with logic wherever the sequencing they represent is genuine. Open-ended logic sits at exactly 5.0%, on the warning boundary; closing the successor links on the MEP rough-in chain (A1801 and its siblings) would recover both the open-ends and the out-of-sequence checks.

Net effect on the forecast finish is an 18-day slip to 19 November 2027, recoverable with constraint cleanup and resequencing of the Grid G erection. Every figure in this narrative is traced to the activities listed in section 3.

Basis and limitations

Illustrative example

Produced from fictional project data for illustration. No real schedule, client or contractor data is used or implied.

ScheduleInsight · Schedule Quality Report6
Appendix A · Check register28 Feb 2026

A Full check register — all 18 checks

Every check with its measured value, the target applied and the result. Checks 1–14 are the DCMA 14-point assessment; 15–18 are the additional checks.

#CheckValueTargetResult
1Missing logic (open ends)5.0%<5%WARN
2Logic density2.52.0–3.5PASS
3Finish-to-start relationships86%>80%PASS
4Lags3.1%<5%PASS
5Leads (negative lags)6ZeroFAIL
6Out of sequence11ZeroWARN
7Negative float17ZeroFAIL
8Near-critical (float ≤ 10d)8.2%<10%PASS
9High float (> 44d)9.4%<10%PASS
10Critical path percentage12%<15%PASS
11CPLI0.94≥1.0WARN
12High duration (> 44d)4.2%<5%PASS
13Insufficient detail3.8%<5%PASS
14Hard constraints3.1%<2%FAIL
15Soft constraints4.4%<5%PASS
16Milestone coverage2.6%>2%PASS
17BEI (baseline execution index)0.91≥1.0WARN
18SPI (schedule performance index)0.93≥1.0WARN
Weighted Schedule Quality Score73 / 100
ScheduleInsight · Schedule Quality Report7
Appendix B · Provenance28 Feb 2026

B Movement since baseline, and provenance

Which checks moved between the R10 baseline and this revision, and by how much. Only checks whose result changed or whose value moved materially are listed.

#CheckR10R12Result changePoints
7Negative float417WARN → FAIL−3
14Hard constraints1.4%3.1%PASS → FAIL−2
11CPLI0.990.94WARN → WARN−1
1Missing logic (open ends)7.1%5.0%FAIL → WARN+1
17BEI0.950.91WARN → WARN−1
Net movement, R10 → R12−4

Check 1 is the only improvement, and it is a disclosure rather than a gain: closing open-ended logic revealed delay that was previously invisible. A programme whose only improving check is an honesty correction is worth reading carefully.

Source file
TowerC_R12_2026-02-28.xer
Baseline
TowerC_R10_2025-11-30.xer
Data date
2026-02-28
Activities / links
3,842 / 9,610
Method
DCMA 14-point + 4
Computation
In-browser, file not uploaded
Where this report sits in the set

This is the entry assessment: how the network is built. The Programme Assurance Review adds three further layers — contract compliance, execution readiness and completeness — and returns an accept / accept-with-comments / reject decision. The Executive Brief distils this report for a board and is included with it.

ScheduleInsight · Schedule Quality Report8

This took one upload and about eight minutes.

Load your own Primavera P6 or Microsoft Project schedule and explore every metric free — the viewer, the scoring, the drill-downs. You only pay when you want the report. No card required to look.

The quality score is the entry assessment. There are three more layers.

The Programme Assurance Review takes the same file further: contract compliance against NEC4, JCT or FIDIC; whether the phases actually hand off to each other in the logic; and whether the programme models the whole job through to handover. It returns an accept / accept-with-comments / reject decision across 21 pages.